Milestone: 1: Initial Test Setup

No date set

43%

Number of tickets:
closed:
6
active:
8
Total:
14

To reach this milestone, the build system should be set up properly as well as an appropriate directory hierarchy. Primarily, the fake systems (testing platform) should be complete.

Both AGG and OpenGL 1.2 software rendering accelerant modules and libraries should be functional.

Integrate into Haiku alongside the app_server.

Implement hardware acceleration. The current design enables Indirect Drawing.

Modifying the system to use direct drawing would require giving the clients the capability to write directly to the driver's ringbuffer. Other considerations include where to maintain state, etc.

Milestone: Documentation

No date set

25%

Number of tickets:
closed:
1
active:
3
Total:
4

Create an appropriate amount of documentation to explain the workings of the system for future additions/maintenance(/porting).